Latest revised building timeline

This month we have received a revised building timeline from the Ministry of Education.

Design phase – March 2015 – March 2016.  This is broken down into 4 phases:

  • master plan – 3 months (Mar 2015 – June 2015)
  • preliminary design – 3 months (July 2015 – Sep 2015)

We are now moving into this next phase:
  • developed design – 3 months (Oct 2015 – Dec 2015)
  • detailed design – 3 months (Jan 2016 – Mar 2016)
  • tender/consent – 2 / 3months (Mar 2016 – Apr/May 2016 – highly dependent on how it takes for CCC to approve documentations.  Cannot commence construction until this has been received).
  • Construction commence – Apr/ May 2016 with an estimate of 12 – 18 months construction period. 

 The above is subject to movement depending on what happens with decanting and the construction methodology. 