As you will have probably noticed, our West Hub is looking very close to being ready. I was fortunate to have a look inside again this week and the ceiling tiles and wall coverings were nearly all in. The joinery units are mostly in, and carpet is due to go down this coming week. The last major pieces of work will be the installation and commissioning of the underfloor heating system and the final landscaping pathway work around the outside of the building.



The East Hub is also moving along quickly and both are on track to be ready for our Y1-4 classes to move into them for the start of Term 3.

The new Bike Stand are is working well. Special thanks Fahey Fencing who have loaned us the temporary fencing for no charge. When we get the permanent fencing installed, we will be looking to have two gates, an 'in' and an 'out' gate, to improve the flow of traffic at peak times.